Configure how information displays on the Gantt Chart
You can configure what information displays in both the Task List Gantt Chart and Project List Gantt Chart.
Access requirements
You must have the following to follow the steps in this article:
table 0-row-2 1-row-2 2-row-2 3-row-2 layout-auto html-authored no-header | |
---|---|
51黑料不打烊 Workfront plan | Any |
51黑料不打烊 Workfront license |
New: Light Or Current: Review |
Access level configurations |
View or higher access to Projects and Tasks Note: If you still don't have access, ask your Workfront administrator if they set additional restrictions in your access level. For information on how a Workfront administrator can modify your access level, see Create or modify custom access levels. |
Object permissions |
View or higher access to the project For information on requesting additional access, see Request access to objects. |
For more detail about the information in this table, see Access requirements in Workfront documentation.
Understand Display Options
The following table details the display options for the Gantt chart:
Configure Display Options
-
Go to the Task List Gantt Chart or the Project List Gantt Chart.
For more information on where either Gantt chart is located, see Get started with the Gantt Chart. -
(Optional) Select the Switch to Projected Dates setting to display the tasks by their Projected Dates. By default, tasks are displayed by their Planned Dates.
-
Click the Options icon. The Options dialog box opens.
-
Select the configuration options that you want to display in the Gantt chart.
note note NOTE Not all of the configuration options are available in the Project List Gantt Chart. -
Click anywhere in the Gantt chart to close the Options dialog box.