Edit tasks in a list edit-tasks-in-a-list
You can edit task information in a list of tasks by editing the fields displayed in the list. For information about other ways to edit tasks, see Edit tasks.
Access requirements
table 0-row-2 1-row-2 2-row-2 3-row-2 layout-auto html-authored no-header | |
---|---|
51黑料不打烊 Workfront plan | Any |
51黑料不打烊 Workfront license |
New: Standard Current: Work or higher |
Access level configurations |
Edit access to Tasks and聽Projects Note: If you still don't have access, ask your Workfront administrator if they set additional restrictions in your access level. For information on how a Workfront administrator can change your access level, see Create or modify custom access levels. |
Object permissions |
Contribute or higher permissions to the task and the project For information on requesting additional access, see Request access to objects. |
For more detail about the information in this table, see Access requirements in Workfront documentation.
Considerations about editing tasks in a list considerations-about-editing-tasks-in-a-list
Editing tasks in a list is a fast way to make changes to multiple tasks simultaneously with a clear view of how your changes might affect the project timeline.
Consider the following when editing tasks in a list:
-
Unlike needing Manage permissions to the task when editing it in the Edit Box, you can edit a task in a list only with Contribute permissions to the task. This allows you to edit the following limited information for the task:
-
Description
-
Status
-
Percent Complete
-
Custom聽Form information
note note NOTE You can edit a task custom field in a list only if you have permissions to update the field. -
Log hours
-
Modify Assignments
-
View finance information
-
Add expenses, tasks, or issues
-
-
You can edit a task in the following lists:
-
The Tasks section of the project
-
The Subtasks section of the project
-
A task report
note note NOTE By default, Workfront automatically saves your changes to tasks in the Subtasks section or in a task report.
-
-
You can control when Workfront saves the changes you make to the tasks in a list. Your changes can be saved automatically or you can manually save them.
For information about configuring when Workfront saves changes you make to tasks in a list, see the Select a save option when editing tasks in a list section in this article.
-
Other users must refresh their pages before they can view the updates you make to a task.
Select a save option when editing tasks in a list select-a-save-option-when-editing-tasks-in-a-list
You can decide whether the changes you make to tasks in a list are saved automatically as they occur, or if you want to manually save each change.
When you save your changes in a list for a project that has either Automatic or Automatic and On Change selected as the Update Type, Workfront updates the project timeline, along with all in-project and cross-project dependencies. Timeline calculations can take a long time if the project is large or if there are a lot of dependencies. Some methods of editing a task list can be faster than others, depending on the method you select to save your changes.
You can control when Workfront saves the changes you make to the tasks in a list. The following scenarios exist:
-
You can have Workfront automatically save the changes, after each update.
For information, see the section Edit tasks in a list and automatically save changes in this article.
-
You can have control over when you apply multiple changes at a time by manually using a Save button.
For information, see the section Edit tasks in a list and manually save changes in this article.
Edit tasks in a list and automatically save changes edit-tasks-in-a-list-and-automatically-save-changes
Consider the following when saving your task list changes automatically:
- You can apply a custom view to the task list and edit any task-related fields that you have access to update.
- You cannot reverse auto-saved changes. This is the default setting.
- When the project Update Type is Automatic or Automatic and On Change, Workfront recalculates the timeline of the project and all the in-project and cross-projects dependencies automatically after every change. For information about the project Update Type, see Select the project Update Type.
To edit tasks in a list and save changes automatically:
-
Click the Main Menu icon
-
On the Projects page, select a project.
-
In the left panel, click the Tasks section.
-
Click the Plan mode icon
-
Edit any field that you have permissions to update manually.
-
(Optional) Press Escape to cancel your changes.
-
Press Enter (Windows) or Return (Mac) on your keyboard to save your changes to the tasks and the project timeline.
-
(Optional) Right-click a task you want to modify.
Or
Click the More menu
-
(Optional) Select from the following options:
table 0-row-2 1-row-2 2-row-2 3-row-2 4-row-2 5-row-2 6-row-2 7-row-2 8-row-2 9-row-2 layout-auto html-authored no-header Open in New Tab Opens the task in a new browser tab. Insert Task Above Inserts a task above the selected task. Insert Task Below Inserts a task under the selected task Edit Opens the Edit Task box, where you can edit the task.
For information about editing a task, see Edit tasks in a list.
Delete Deletes the task.
For information about deleting tasks, see Delete tasks.
Indent Indents the task by one level.
This option displays only on stand-alone tasks.
Outdent Outdents the task by one level.
This option displays only on children tasks.
Duplicate Creates a duplicate version of the task within the same project. Copy to... Copies the task to another project.
For information about copying and duplicating tasks, see Copy and duplicate tasks.
Move to... Moves the task to another project.
For information about moving tasks, see Move tasks.
Edit tasks in a list and manually save changes edit-tasks-in-a-list-and-manually-save-changes
You can manually save changes you make to tasks in a list. When you save changes this way, you have the flexibility to reverse them before saving.
- You cannot reverse changes you make to tasks in a list when you are editing them in the Subtasks section or in a task report.
- There are no limitations on how many changes you can reverse. You can reverse all of them one-by-one until you reach the original state of the tasks.
Consider the following when saving changes in a task list manually:
-
In order to save task list changes manually, you need permissions to Manage both the tasks and the project.
-
You cannot edit the project. The option to edit the project is disabled.
-
You cannot update information in the header of the project. You can only do the following when manually saving the changes in the task list:
- Subscribe to the project.
- Add the project to your list of favorites.
- Open a task by clicking its name in the list.
-
Edit the tasks in bulk. The Edit icon is disabled when selecting multiple tasks.
-
Workfront triggers notifications about the changes you make to the tasks only after you save your changes.
There are 2 ways to manually save changes to tasks in a list:
Save changes in a task list manually when you select the Manual save Standard option save-changes-in-a-task-list-manually-when-you-select-the-manual-save-standard-option
Consider the following when updating tasks in a list after selecting the Manual save Standard option:
- You can apply a custom view to the task list and edit any task-related fields that you have permissions to Manage in that view.
- When the project Update Type is Automatic or Automatic and On Change, Workfront calculates the timeline of the project and all the in-project and cross-project dependencies after you click Save. For information about the project Update Type, see Select the project Update Type.
To edit tasks in a list when selecting the Manual save Standard option:
-
Click the Main Menu icon
-
On the Projects page, select a project.
-
In the left panel, click the Tasks section.
-
Click the Plan mode icon
-
In the Plan Mode dialog, select Manual save, then click Standard.
-
Click Apply. A toolbar setting displays with options to undo, redo, and save your changes.
-
Click inside any field that you have permissions to update manually. The field becomes editable and you can make your changes.
-
Press Enter (Windows) or Return (Mac) on your keyboard to temporarily save the changes you made.
-
(Optional) Click the Undo icon
-
(Optional and conditional) Click the Redo icon
-
(Optional) Right-click a task you want to modify.
Or
Click the More menu
-
(Optional) Select from the following options:
table 0-row-2 1-row-2 2-row-2 3-row-2 4-row-2 5-row-2 6-row-2 layout-auto html-authored no-header Open in New Tab Opens the task in a new browser tab. Insert Task Above Inserts a task above the selected task. Insert Task Below Inserts a task under the selected task Delete For information about deleting tasks, see Delete tasks. Indent Indents the task by one level.
This option displays only on stand-alone tasks.
Outdent Outdents the task by one level.
This option displays only on children tasks.
Duplicate Creates a duplicate version of the task within the same project.
For information about copying and duplicating tasks, see Copy and duplicate tasks.
-
Workfront updates all in-project and cross-project dependencies when you make changes to the timeline of tasks.
-
Click Save when you want to keep your task changes permanently and save the timeline of the project.
Save changes in a task list manually when you select the Manual save Timeline Planning option save-changes-in-a-task-list-manually-when-you-select-the-manual-save-timeline-planning-option
Saving your changes and all the project dependencies is faster. This is not available for projects with more than 2000 tasks.
Consider the following when using the Manual save Timeline Planning option in a task list:
- You cannot apply Manual save Timeline Planning option to projects that have more than 2000 tasks.
- You cannot apply a custom view, filter, or grouping to the task list. The View, Filter, and Grouping drop-down menus, as well as the Agile view icon, are disabled. The view that is applied by default contains a limited number of fields.
- The timeline of the project and all the in-project dependencies are calculated automatically after each change when the project Update Type is Automatic or Automatic and On Change.
- When the project Update Type is Automatic or Automatic and On Change, the cross-project dependencies are calculated after you click Save. For information about the project Update Type, see Select the project Update Type.
To edit tasks in a list when using the Manual save Timeline Planning option:
-
Click the Main Menu icon
-
On the Projects page, select a project.
-
In the left panel, click the Tasks section.
-
Click the Plan mode icon
-
In the Plan Mode dialog, select Manual save, then click Timeline Planning.
note tip TIP The Time Planning option is dimmed for projects with more than 2000 tasks. -
Click Apply.
The following changes occur in the list:
-
The View, Grouping, and Filter drop-down menus are removed and the view is replaced by the following fields:
- Task Number
- Task Name
- Constraint Type
- Duration
- Planned Start Date
- Planned Completion Date
- Predecessors
- Assignments
- Status
- Percent Complete
-
The Agile view icon is removed.
-
A toolbar setting displays with options to undo, redo, and save your changes.
-
-
Edit any field that you have permissions to update manually.
-
Press Enter (Windows) or Return (Mac) on your keyboard to temporarily save the changes you made.
-
(Optional) Click the Undo icon
-
(Optional and conditional) Click the Redo icon
-
(Optional) Right-click a task you want to modify.
Or
Click the More menu
-
Select from the following options:
table 0-row-2 1-row-2 2-row-2 3-row-2 4-row-2 5-row-2 6-row-2 layout-auto html-authored no-header Open in New Tab Opens the task in a new browser tab. Insert Task Above Inserts a task above the selected task. Insert Task Below Inserts a task under the selected task Delete For information about deleting tasks, see Delete tasks. Indent Indents the task by one level.
This option displays only on stand-alone tasks.
Outdent Outdents the task by one level.
This option displays only on children tasks.
Duplicate Creates a duplicate version of the task within the same project.
For information about copying and duplicating tasks, see Copy and duplicate tasks.
-
Workfront updates all in-project and cross-project dependencies when you change the timeline of a task.
-
Click Save when you want to keep your task changes permanently and save the timeline of the project.
Edit a task in a list using the Summary
-
Click the Main Menu icon
-
On the Projects page, select a project.
-
In the left panel, click the Tasks section. The list of tasks on the project displays.
-
Select the task you want to edit, then click the Open Summary icon
-
(Optional) Type an update for the task in the Updates area.
-
Click any of the following icons or areas to go to the task and edit information at the task level:
- Click the X in the top-right corner of the panel to close it.
Edit tasks in bulk
You can edit multiple tasks all at once. Ensure you have manage permissions to the tasks to be able to edit them.
-
Click the Main Menu icon
-
On the Projects page, select a project.
-
In the left panel, click the Tasks section.
-
Click the Plan mode icon
note important IMPORTANT You can鈥檛 edit tasks in bulk when saving tasks manually. -
Select more than one task in the tasks list.
-
Click the Edit icon
-
Specify the information you want to change for all the tasks you selected.
Editing the information on all tasks is identical to editing information on one task. If you want to edit task Duration, the tasks selected must have the same Task Constraint; otherwise, the Duration field does not populate.
For more information about editing a task, see Edit tasks.
note note NOTE The information you are changing on all the tasks selected will override the existing information on individual tasks, except for the Assignments field. Adding a new assignee in bulk edit will add that assignee to all the selected tasks. If other assignees are assigned to the selected tasks, they will remain assigned in addition to the one added through bulk edit. -
Click Custom Forms to edit the custom forms attached to all the tasks selected. Only active custom forms display in the list.
If the tasks selected do not have any common custom forms, no forms are listed in this section.
You can edit only the fields on the forms that are attached to all tasks selected and which you have permissions to edit.
-
(Optional) In the Custom Forms section, select the Recalculate Custom Expressions option to ensure that all Calculated Custom Fields that are on the custom forms attached to the tasks selected are up to date.
-
Click Save Changes. All changes you made are now visible on all the selected tasks.
For information about bulk editing custom forms, see Manage custom forms attached to objects.